This procedure describes how to assign a 'completion required by' date and time to each workflow step for each task in a project.
Procedure
- Display the project on the <Project Name> - Details screen (see Accessing projects).
- Click Schedule Steps. The Schedule Steps screen is displayed. By default, all tasks in the project are displayed. Unscheduled steps are shown in red.
- Display the tasks to be scheduled:
- If you want to display all tasks that are at a particular workflow step, select the step in the Workflow Step box.
- If you want to display all tasks for a single language pair, select the language pair in the Language Pair box.
- In the Due Date column, click the calendar icon
. The calendar is displayed for completion.
- Select the date and time by which the step should be completed. When you have finished, click to save the values and close the calendar.
Note: If you want to assign the same date and time to all of the displayed tasks, click the calendar icon on the bottom bar of the Schedule Steps screen.
- When you have finished scheduling the displayed steps, click Submit. This saves the changes you have made. The scheduled steps are no longer displayed in red.