Steps in Single Projects
The Task List for each project displays information that helps you assess the state of each task. To display the Task List, go to and click on an item in the Project Name column.
For each step, the following columns can help you monitor the state of a task.
- Assigned To
- Human step = the names or roles of the assignees
- Status
-
Human step = an icon.
Click the icon to see a list of possible statuses.
- Comment
- A textual description of the status
Task List Information
With this information, you can answer questions such as the following:
- What is the status of my work?
By examining the Task List, you can assess when work might be completed and perhaps more effectively communicate this information to your customers.
- How long has a task been running?
For a given step that is running, does the elapsed amount of time seem excessive for the work to be performed? If so, you may want to investigate further.
- Does the priority of a particular task need to be changed?
If an urgent step is preceded in the queue by many other steps, you may want to change the priority of the task to move the step up in the queue.