To move a Task

You can move Tasks to another Project with the same Locale or to a new Project. Depending on whether you choose to move the Tasks to an existing Project or to a new Project, you either select the existing Project, or specify a name, description, and Workgroup for the new Project.

Procedure

  1. From the Task view, select one or more Tasks that you want to move.
  2. On the Tasks ribbon, click Task Options > Move Task(s).
    WorldServer displays the Move Tasks dialog box.
    • To move the Task to an existing Project, choose the Project from the Project list and click OK.
    • To move the Task to a new Project, specify a Project name (mandatory), description and workgroup for the project.
  3. Click OK.