Changing the project due date

Procedure

  1. Select Home tab > Project Settings from the Ribbon. The Project Settings dialog box for the active project is displayed.
  2. Select Project from the navigation tree. The Project settings are displayed on the right.
  3. If the check box next to Due Date is not selected, select it now.
  4. To change the project due date, type a new date over the existing date or click the arrow to the right of the date and select a new date from the calendar that is displayed.
  5. To change the project due time, type a new time over the existing time or click the up and down arrows to change the time.
  6. Click OK to save your changes to close the Project Settings dialog box.