Changing the project due date
Procedure
- Select Home tab > Project Settings from the Ribbon. The Project Settings dialog box for the active project is displayed.
- Select Project from the navigation tree. The Project settings are displayed on the right.
- If the check box next to Due Date is not selected, select it now.
- To change the project due date, type a new date over the existing date or click the arrow to the right of the date and select a new date from the calendar that is displayed.
- To change the project due time, type a new time over the existing time or click the up and down arrows to change the time.
- Click OK to save your changes to close the Project Settings dialog box.