Durée des projets avec modèle de planification
If the project includes a project schedule, the task duration is calculated depending on several factors. Familiarize yourselves with all the scenarios before setting up your project schedule.
Scenario 1: All Human workflow tasks have a duration specified in the schedule template
Scenario 1.1. - The total duration of workflow tasks = project duration
The due date of each Human workflow task is calculated based on the task duration specified in the schedule template.
Scenario 1.2. - The total duration of workflow tasks < project duration
The due date of each Human workflow task is calculated based on the task duration specified in the schedule template. Because the project duration exceeds the duration of workflow tasks, the delta duration (the remaining time) is not redistributed among tasks.
Scenario 1.3. - The total duration of workflow tasks > project duration
The due date of each Human workflow task is calculated based on the task duration specified in the schedule template. Because the duration of workflow tasks exceeds the project duration, there will be cases where some or all Human workflow tasks will already be overdue by the time they reach the assignees.